Western Power Indicate 12 weeks Lead Time to Design

Western Power’s Design and Access Offer Application could take up to 12 weeks prior to commencement of a desktop review and estimate quotation. With the following indicative end to end cycle time guidelines from Western Power, these timeframes should be noted and applications submitted in the early stages of the project to avoid/minimise delays and cost implications.

The table below provides indicative E2E cycle time guidelines for each customer access project category:

Project Category Time (Months)
Connection 4
Subdivision 6
Relocation 9
Network Extension 12

Please note the following about these indicative guidelines:

  • Based on the full timeframe from application to energisation.
  • Based on an 80% confidence level.
  • Each project category encompasses a broad range of work.